Building on our strong start with the Joseph Gallagher Ltd contract at Uckfield, we are pleased to announce that we have now secured the earthworks contract for Kier to support their project on the same development. Kier, engaged by UK Power Networks, is constructing a substation alongside the new National Grid one, and the scope of their project closely mirrors the work we are already delivering. In addition to the earthworks, we will be removing 11,500m³ of muck away and importing 7,000 tonnes of stone. This work will run concurrently with the Joseph Gallagher / Balfour Beatty contract. With our expertise and resources, we are confident in our ability to successfully deliver for both projects on schedule.
Removing 11,500m³ of muck away and importing 7,000 tonnes of stone